On site the work runs to the construction phase plan. Access, edge protection, lifting, roof loading and the live electrical interfaces with your building are planned before anyone climbs a ladder, and your facilities team gets a programme saying which areas are affected and when. Most commercial roofs stay in use while we work, and the plan is written on that assumption.
Mechanical installation comes first: the mounting system set out from the surveyed model, ballast or fixings specified against the structural calculation, then modules, DC cabling and containment. Electrical work follows through inverters, AC cabling, protection, isolation and metering. Where the roof needs penetrations, they are weathered to the roof manufacturer’s own detail, so the covering warranty survives.
Commissioning is a test regime rather than a switch. Following IEC 62446-1 we run insulation resistance, polarity and continuity checks, open-circuit voltage and operating current on every string, earth continuity, protection and isolation tests, and the export limitation check the connection depends on. Results are recorded string by string, so a reading taken five years from now has something honest to compare against.
Handover is a file rather than a handshake. You receive the as-built drawings, the electrical installation certificate, the commissioning and test records, the O&M manual, equipment datasheets and warranties, the structural and wind-loading calculations, the DNO paperwork and the monitoring credentials. That set is what an incoming buyer, insurer or funder will ask for, and assembling it after the fact is close to impossible.
For the first twelve months there is a defects-rectification period: anything that proves to be a defect in our workmanship, or in the equipment we supplied, is put right by us. An Insurance-Backed Guarantee sits behind it, so the cover does not depend on the installer still trading. Equipment warranties run for their own terms on top, and we hold the paperwork that lets you claim.