Skip to content
07944 877 329 hello@alectrona.solar

Alectrona

Commercial inverter design · over 50 kWp

The conversion side decides what the roof can do.

The inverter decides how a commercial array is split, what it can export, and what you can see when a section stops earning. This page is the engineering behind that decision, from tracker count and string length to the switchroom, the G99 position and the replacement that comes long before the modules are finished.

  • Survey-led, no from-price
  • Designed to BS 7671 and IEC 62446
  • Over 50 kWp, outside MCS
01 What it decides

The inverter sets the ceiling on everything above it. Roof geometry, the building’s electrical infrastructure and the connection agreement all have to be reconciled here.

An inverter converts the direct current the modules produce into alternating current at the building’s voltage and frequency, and it does that every second of daylight for twenty-five years. On a commercial array it does three further jobs the headline rating does not describe. It holds each group of strings at its maximum power point as irradiance and cell temperature move through the day. It is the only part of the system that negotiates with the network, so it carries the type-test certification, the protection settings and the export setpoint your Distribution Network Operator agrees. And it is the sole source of data about how the array is performing, at whatever resolution its architecture allows.

Because of that, the conversion side is where the shape of the roof, the electrical infrastructure of the building and the terms of the connection have to be reconciled. We design in that order. The survey establishes what the roof can carry and how it is broken up. The model establishes what the array would generate against your own consumption. The network operator establishes what may be exported, which on a constrained network is frequently well below what the roof could push. Only then is the AC architecture set and the inverter chosen to serve it. Reversing that order, picking a platform first and fitting the array to it, is how a good roof ends up with strings grouped badly and a plant room nobody can work in.

There is no price on this page and there will not be one. Above 50 kWp the figure comes from an on-site survey and a half-hourly PV*SOL model run against your own load, so a published number would be a guess wearing an engineer’s coat. What follows is the engineering instead: how the conversion is split across the site, how strings are grouped, what the equipment does to a plant room and a switchroom, what the grid connection requires, and what happens when the electronics reach the end of their life while the modules are still under warranty.

02 Architecture

One inverter, several, or one large machine.

Three arrangements cover almost all commercial work. Each has a point where it stops making sense, which is more useful than a size at which it is simply wrong.

One roof, one orientation

A single string inverter

One three-phase unit takes the whole array. It is the least complicated thing to install, commission and document, and it suits a uniform roof on a single orientation with a short, clean AC route back to the board.

  • Fewest AC terminations and the least added switchgear
  • One firmware version, one commissioning record, one monitoring account
  • DC runs stay short where the unit can sit close to the array

It stops making sense once a single fault would take the whole site off, or once the roof needs more independent trackers than one unit carries.

Most commercial rooftops

A multi-inverter string layout

Several three-phase units, each carrying the strings from one roof area, one pitch or one building. Most commercial rooftops end up here, because the arrangement follows the shape of the building instead of fighting it.

  • A fault or a firmware problem costs one unit’s share, not the array
  • Sections can be energised in phases as a building is built out or occupied
  • Each unit sits near its own strings, which shortens the DC side
  • Trackers can be grouped by orientation across the whole roof

It stops making sense when the number of units makes the AC combining, the commissioning and the spares position cost more than the redundancy is worth.

Large uniform ground-mount

A central inverter

One large machine, or a rack of string units in a housing, sitting beside a transformer and taking the whole plant. This is ground-mount territory: one orientation, uniform rows, a connection made at higher voltage.

  • Lowest cost per kilowatt at scale, with far less repeated switchgear
  • Needs a housing or plant room, hardstanding and a maintenance access route
  • Concentrates the grid interface in one place, which suits deep plant control

It stops making sense on a broken-up roof, where one machine cannot track separate orientations and any outage takes the entire array with it.

None of the three is a default. The arrangement is chosen from the survey, the export position and how the building is used, and we tell you which one we are proposing and why.

Module-level power electronics sit on a different axis from that choice rather than forming a fourth option. A DC-optimised design puts an electronic device at each module, which recovers yield where shading from rooftop plant, parapets, flues or a neighbouring building would otherwise drag a whole string down, reports per module, and de-energises the DC at each module for maintenance crews and first responders, the behaviour RC62 fire-safety guidance looks for. It also adds a component per module on the roof, so we specify it where the survey shows shading or complexity that earns it, and not as a habit. The fuller comparison of distributed against central conversion, including redundancy, serviceability and phasing, is in the string versus central inverters guide. Where storage is in the scheme, whether the battery is AC-coupled alongside the PV inverters or handled by a hybrid unit is settled on the battery storage side and then reflected back into this layout.

03 Strings and trackers

String design is arithmetic before it is preference. Tracker count decides how finely the roof can be divided; temperature decides how long a string may be.

A maximum power point tracker is an independent input that finds and holds the voltage at which the strings connected to it produce the most power. The number of trackers on a unit therefore decides how finely the roof can be divided. Every string on one tracker is pulled to a shared operating point, so strings that face different ways, sit at different tilts or shade at different times of day should not be sharing one. An eight-tracker machine on a plain south-facing roof buys nothing it can use; a two-tracker machine on a roof with five pitches quietly gives up output every morning and every afternoon for the life of the asset.

String length is fixed by voltage rather than by how the layout looks on a drawing. A module’s open-circuit voltage rises as cell temperature falls, so the longest permitted string is set by a cold, bright winter morning: the series count has to keep the array below the inverter’s maximum DC input, commonly 1,100 V on the three-phase commercial units and 1,500 V on the platforms used for large ground-mount. The shortest string is fixed at the other end of the year, by the warmest afternoon, when the operating voltage still has to sit inside the tracker’s working window or the unit falls off its maximum power point at the moment there is most light to collect. Strings sharing a tracker are kept to the same length and the same orientation for exactly the same reason.

The ratio between array size and inverter rating is then a deliberate decision rather than an accident of what was in stock. A commercial array is normally oversized against its inverters, because a UK roof spends very little of the year anywhere near its rated output, and the additional modules earn through the whole of a dull morning while the loss at the peak of a clear June day is small and brief. Where the network operator has capped export, the arithmetic changes again, since the ceiling is then the connection rather than the equipment, and the surplus is worth more used inside the building than pushed at a limit that will not take it. We model that clipping in PV*SOL against your half-hourly consumption, so the ratio is chosen with the loss quantified rather than by rule of thumb.

Design constants

The numbers that bound the design.

Datasheet limits and connection requirements, not performance promises. Every one of them is confirmed against the issued datasheet for the specific unit before it is specified.

  • 1,100 V Typical maximum DC input on a three-phase commercial inverter 1,500 V platforms are used for large ground-mount
  • 5 to 12 Independent MPP trackers on the commercial units we specify the count sets how finely a roof can be grouped
  • G99 G99 compliance the exact model and firmware must show full or partial type test, checked on the ENA register before specification
  • At least 1 Inverter replacement to design for across the array’s life the module warranty outlives the electronics
A commercial rooftop solar array
04 Plant room and switchroom

The equipment has to live somewhere, and be reached again. Above 50 kWp the conversion side stops being a box on a wall and starts being plant.

Inverters reject heat, and they derate when they cannot, so position is chosen for airflow rather than for tidiness: outdoors on a shaded wall, or inside a room with genuine ventilation, never in a sealed cupboard that becomes an oven in July. Enclosures rated to IP65 or IP66 will sit outside without a separate cabinet, though direct sun on the case still costs output over a long summer, and fan-cooled units make a noise that matters next to an office window or a residential boundary. On a ground-mount scheme the same questions become a housing, a hardstanding and a track that a vehicle can still use in February.

The AC side is usually where the surprises are. The distance from the array to the intake drives cable size, because volt drop has to stay inside the limits BS 7671 sets, and on a long industrial building that pushes the cable larger than the current alone would suggest. Several inverters have to be combined, which means an AC combiner or a dedicated distribution board, and then a way in to the existing switchgear. Spare ways in the main panel, the prospective fault level at that board, the rating of the incoming supply and the physical room to land a new cable are all checked at survey, because a switchroom with nothing spare in it is a programme item rather than a detail. On a larger scheme it can be the item that decides where the inverters go.

Access is designed in from the start. A commercial inverter is a two-person lift or a mechanical one, and it has to be carried in when it is installed and carried back out when it is replaced, past whatever the building has become by then. We keep clear working space in front of every unit, label the DC and AC isolation so it reads correctly to somebody who has never seen the system, and record the stringing on the as-built drawings. Design, inspection and verification sit under BS 7671 and IEC 62446 rather than MCS, because a system this size is outside the domestic scheme, and the works run under CDM 2015 with a principal designer and a real construction phase plan. Our quality without MCS guide sets out what that assurance stack covers and what it replaces.

05 Grid position and data

What the network requires, and what you can see afterwards. The connection offer is the ceiling the rest of the design is built to.

Every inverter on a commercial connection needs G99 compliance evidence for the exact model and firmware. A full type test on the ENA register carries that case, and the current edition of G99 grants that status only to units of 50 kW or less; a larger unit usually carries a partial one, which covers part of the case, with the rest supplied with the application and shown at commissioning. We check which applies against the register rather than take it from a brochure. The G99 application runs in parallel with the design, because the offer that comes back sets the ceiling everything else is built to. The network operator may grant full export, may cap it, or may offer a connection on the condition that nothing is exported at all, and on a constrained part of the network that answer arrives late enough to be the longest single item in the programme. We start it early for that reason and size the array to the position the operator confirms.

Where export is limited, the limit has to be enforced rather than promised. That means a metering point at the intake, current transformers on the incoming supply and a controller that instructs the inverters to reduce output inside the response time the operator specifies, which is the arrangement our export limitation and G100 guide describes. The inverter has to be able to accept that setpoint and to fail to a safe state if the controller stops talking to it, so the capability is confirmed at specification and then demonstrated at commissioning in front of the witness the scheme requires. A design that relies on everyone remembering not to export is not a design.

Monitoring resolution follows the architecture. A string inverter reports at unit and string level, which is enough to show that one group has dropped away; a DC-optimised design reports per module, so a single failed or shaded panel is visible instead of being averaged into a total that still looks broadly right. Either way the portal account is created in your name with the data exportable, so the performance record does not sit inside a contractor’s login and leave with them. That feed is what our operations and maintenance work runs on, and it is the difference between catching a fault in a week and catching it in an annual bill. The symptoms worth watching for are set out in our performance audit.

07 The roster

Which manufacturer is settled after the design, not before it.

The corporate story, the ownership, the manufacturing footprint, the warranty terms and the honest caveats for every maker we specify are written once, on one page per manufacturer, covering everything that maker supplies to us instead of repeating itself across product categories. The full roster of modules, inverters and storage sits at the manufacturer directory, alongside the module and storage sides of the same design.

Two things stay fixed wherever a scheme lands. An inverter is never described here as BloombergNEF Tier 1, because that is a module financeability scheme and attaching it to conversion equipment would be borrowing a credential that does not apply; there is a separate inverter bankability survey, and it is cited only on the page of a maker that genuinely leads it. And where a manufacturer carries a real financial or track-record caveat, it is stated on that maker’s page rather than quietly left out. Our reasoning on the brands we decline to specify is set out in the why we do not specify Huawei guide.

FAQ

Commercial inverters: common questions

It comes out of the roof, not out of a preference. A uniform single-pitch roof can run on one three-phase unit; a building with several pitches, a phased occupation or separately metered units usually ends up with several, each carrying the strings from its own area. The count is settled by tracker requirements, cable runs back to the intake, how much of the array you are prepared to lose to one fault, and whether sections need to come on line at different times. We set it out in the design with the reasoning attached, so it is a decision you can question rather than a number you are handed.

Usually not, and deliberately so. A UK commercial roof spends very little of the year at its rated output, so an array is normally oversized against the inverters: the extra modules earn through dull mornings and long shoulder seasons, while the clipping at the top of a clear summer day is short and small. How far to take that depends on your orientation, your consumption shape and whether the network operator has capped export, since a cap moves the ceiling from the equipment to the connection. We model the clipped energy in PV*SOL against your half-hourly data and show you the trade rather than applying a standard ratio.

Somewhere with airflow, access and a sensible cable route. Outdoor-rated units can sit on a shaded external wall or in a plant area; indoors they need a genuinely ventilated room rather than a cupboard, because a hot inverter derates and loses you output in exactly the weather that should be earning. The AC side then needs combining and landing into the switchgear, so the survey checks spare ways in the main panel, the fault level, the incoming supply rating and whether there is room to bring a new cable in. On some sites that switchroom work, rather than the roof, is what sets the programme.

The array is designed to the limit and the limit is enforced in hardware. Export limitation under G100 uses metering and current transformers at the intake with a controller that reduces inverter output inside the operator’s specified response time, and it has to fail safe if that controller loses communication. The inverter is then selected partly on whether it accepts that control properly, and the whole arrangement is demonstrated at commissioning. A cap usually shifts the design towards self-consumption and, on some sites, towards storage, so the surplus is used or shifted in the building instead of being thrown at a connection that will not take it.

Expect the electronics to be replaced at least once during the life of an array whose modules are warranted for decades. Warranty terms vary by model and by UK purchasing channel, with extensions available on most platforms, so we confirm the term and the support route in writing for the specific unit before contract rather than quoting a general figure. In a multi-inverter layout a failure takes out that unit’s share of the array and the rest keeps running, which is a large part of why the arrangement is used. We design the mounting, isolation and working space so a swap is a planned visit rather than a rebuild.

After. The survey and the PV*SOL model set the array, the tracker requirement, the AC architecture and the export position, and the inverter is then chosen to serve that. Choosing the other way round is how roofs end up with strings grouped to suit a machine. What the manufacturer has to satisfy is procurability on a real lead time, current G99 type-test certification for the exact model, spares and firmware support through the asset’s life, and a UK warranty route that exists in practice rather than on paper. Where a maker we list meets one of these only in part for a given model, such as warranty terms that do not name the UK, its page says so and sets out what we do about it. The makers we specify are listed at the manufacturer directory.

Get a commercial quote

Tell us about the roof and the load.

We size the array in PV*SOL, set the export position with your DNO, and specify the conversion side to match it, with the model, the tracker arrangement and the warranty named.

  • On-site 3D drone survey and PV*SOL model
  • We handle the DNO and the G99 connection
  • Over 50 kWp, outside MCS