Skip to content

Alectrona

Commercial solar by system size

Commercial solar at 1 MW and above.

At a megawatt and above, the build is decided as much by the grid as by the roof. This is where the DNO connection, network charges and a rooftop-versus-ground-mount choice shape the whole project.

  • Grid queue and network charges
  • Sized from your half-hourly load
  • Over 50 kWp, outside MCS
Reviews

The feedback we work to earn

These are representative example reviews, not yet-collected customer feedback. They are written to illustrate the kind of feedback Alectrona aims to earn and are shown as design placeholders while we gather and verify reviews from our first commercial clients. Alectrona is the commercial solar trading brand of RVTC LTD.

What set Alectrona apart was the documented design pack. We had quotes from three installers, but only Alectrona handed us a full set of drawings, a single-line diagram and a design referencing BS 7671 and the G99 connection process. The whole thing read like an engineering submission rather than a sales brochure. Our M&E consultant reviewed it and signed it off without a single query. That gave the board the confidence to release the capital.

Estates Manager, academy trust (Yorkshire)

Other firms priced our roof off a satellite image and a desktop guess. Alectrona flew an in-house drone survey, fully insured and flown by a qualified commercial drone pilot, and built a 3D model of the actual roof. It picked up plant, vents and a parapet line that a flat aerial photo had completely missed, which changed the panel layout. I would rather find that out at design stage than on the day the scaffold goes up. The accuracy of that survey is the reason I trusted everything that followed.

Facilities Manager, distribution centre (East Midlands)

As a finance director I was wary of being oversold a system bigger than we could use. Alectrona modelled the array against our actual half-hourly consumption data rather than an annual total, so it is sized to what we genuinely draw on site during the day. They were honest that exporting surplus is worth far less than self-consumption, and built the design around that. The capital case stacked up because the engineering was honest, not because the numbers were inflated.

Finance Director, logistics group (North West)

We were undecided between buying outright, leasing and a PPA. Alectrona laid out all three side by side with the pros and cons of each against our balance sheet, instead of pushing the one that pays them best. They were clear about where a PPA makes sense and where capex wins, and pointed us at our own accountant for the tax treatment. The survey and design took a little longer than I expected, but the thoroughness was worth the wait. Genuinely consultative.

Property Director, retail park (West Midlands)

The install crew were tidy and well run, and worked to a clear CDM 2015 plan with a proper site induction and RAMS. What impressed me most was the handover. We received a full commissioning pack with the IEC 62446-1 test results, certification, O&M documentation and an as-built record for our maintenance team. As the people who have to live with this asset for the next twenty years, having that paperwork in order matters enormously. Nothing was left loose.

Operations Director, food manufacturer (Lincolnshire)

I expected the usual hard sell and got the opposite. After surveying our site Alectrona told us one roof section was not worth covering because of shading, and that a smaller, well-sited array was the better investment than filling every square metre. There was no commission-driven upselling and no pressure. For a six-figure capital project, that straight talk is exactly what you want from the people advising you. We will be using them again on our second site.

Managing Director, engineering firm (Sheffield)

This band covers commercial solar from 1 MW (1,000 kWp) upwards: the largest rooftop arrays, ground-mount fields, and multi-site portfolios where a single energy strategy spans several buildings. At this scale a system is no longer a roof retrofit with a bigger inverter count. It is an energy-infrastructure project, with a grid connection, a network-charge position and a financing route that all need designing together.

It suits very large logistics and distribution sheds, cold and chilled storage at scale, heavy manufacturing, food production, data and process loads, estates and campuses, and landowners with the space for a ground array. It also suits organisations running several sites who want one coordinated programme rather than nine separate quotes. If your half-hourly data shows daytime demand in the hundreds of kilowatts to low megawatts, this is your band. If your roofs cannot host a megawatt but you hold the land, the ground-mount route below is the one to read closely.

Every figure here is an engineering rule of thumb, sized to bracket a project before survey. The real numbers come from your half-hourly consumption, a measured roof or site model and a PV*SOL yield study. We never publish a price per kilowatt-peak at this scale, because at a megawatt the connection and civils can move the budget more than the panels do.

OrientationThese are indicative engineering rules of thumb. Your real figures come from an on-site survey and a PV*SOL model of your roof, shading and consumption.

What changes at 1 MW and above: Grid queue and network charges

The fact that defines this band is that the grid stops being a formality and becomes the project's pacing item. Below a few hundred kilowatts the DNO connection is usually a managed step. At a megawatt it can be the longest lead time and the largest single cost variable on the job, and it often dictates the design rather than following it.

Three things activate together at this scale:

  • Connection and capacity. Every commercial array runs under ENA Engineering Recommendation G99. At this scale you are typically a Type B generator and frequently connecting at high voltage (11 kV), which means a formal application, network studies, and mandatory witness testing before the DNO will let you energise. A larger array can need new switchgear, a cable run or a substation, and in a constrained part of the network it can need reinforcement. Recent reform of the connections process has shifted the queue toward a readiness basis, so projects that can show planning progress and land control tend to be prioritised. The practical implication is simple: start the grid conversation first, because it sets the calendar.
  • Export limits shape the design. Where full export capacity is not available, a limited-export or zero-export connection under ENA G100 lets the project proceed at an agreed maximum export limit instead of waiting for capacity. That pushes the design toward self-consumption and storage, because any surplus the site cannot use or store is curtailed. Designing for what you consume, not what the roof could theoretically generate, is the right instinct at a megawatt.
  • Network charges become material. Transmission (TNUoS) and distribution (DUoS) charges are a real line on a large site's energy bill, and the way they fall on half-hourly sites has been changing in recent charging reviews. Solar offsets daytime import directly; pairing it with battery storage lets a site shift load away from the peak DUoS red band and the winter demand peaks that drive these charges. At this scale the charging position is part of the business case, which is exactly why a megawatt project should never be costed as a panel count alone.

Because all of this is live at once, the genuine question at a megawatt is often not only what to buy but whether to buy at all. A power purchase agreement (PPA), where a developer funds, owns and maintains the array and you pay for the electricity it produces, is a real alternative to outright purchase here. The trade-off between owning the asset and buying the power is a board decision, and we model both so you can take it on evidence.

At a glance
  • System size 1 MW and above
  • Modules 1,665–1,850 modules per MW
  • Roof area 5,000–7,000 m² rooftop, or 2–2.5 hectares ground-mount, per MW
  • Annual output 850,000–950,000 kWh per MW Yorkshire, indicative

What drives the cost at this scale

At a megawatt and above we do not publish a price per kilowatt-peak, and you should be wary of any installer who does. The reason is structural: at this scale the cost is driven less by the modules and more by the things around them, and those vary site by site.

What actually moves a megawatt-scale budget:

  • The grid connection. The single largest variable. A straightforward connection is modest against the whole; a high-voltage connection needing new switchgear, cabling or a substation, or reinforcement in a constrained area, can run to a substantial share of the project. This is why we open with the DNO, not the roof.
  • Rooftop versus ground-mount. A roof array reuses an existing structure but depends on its load capacity, age and layout. A ground array needs racking, foundations, fencing, cable trenching and civils, and the land itself. The two routes have genuinely different cost shapes, and we cost the one that fits your site.
  • Modules, inverters and the DC and AC system. Large commercial modules and string or central inverters, plus the DC strings, AC distribution, switchgear, metering and protection. Volume helps here, which is where scale economics show up.
  • Mounting, access and structure. Structural survey and any strengthening on a roof; ballast or penetration design; scaffold, edge protection and access for a site of this size. Larger jobs carry more access and safety provision, not less.
  • Storage, where it earns its place. Battery storage is frequently bundled at this scale, both to lift self-consumption against an export limit and to manage network-charge peaks. It is a design decision with its own return, modelled separately.

The scale economics are real and run in your favour, but only directionally: as the system grows, the cost for each kilowatt-peak tends to fall, because fixed elements such as design, mobilisation and some grid and access works spread across more capacity. That is a true statement of direction, not a number, and the connection cost can pull against it on any given site. We will not put a figure on it before we have seen yours.

For the indicative engineering picture at 1 MW, using commercial rules of thumb: roughly 1,665 to 1,850 modules at 540 to 600 W panels (about 1.7 to 1.85 modules per kWp); roughly 5,000 to 7,000 m² of usable flat roof per MW once row spacing is allowed, against roughly 2 to 2.5 hectares for the same megawatt as a ground array; and a modelled annual output around 850,000 to 950,000 kWh per MW on a Yorkshire yield of roughly 850 to 950 kWh per kWp installed. Treat every one of these as indicative and bracketing only. The figures that go in a board paper come from your measured roof or site, your half-hourly demand and a PV*SOL study, never from a table.

For payback, internal rate of return and bill-reduction modelling at this scale, we keep those figures on the pages built to carry them properly, with their assumptions stated: see our commercial solar finance options and our commercial solar ROI and payback guide. The only fixed third-party figure worth noting here is the Annual Investment Allowance: capital expenditure on solar qualifies for 100% relief in the year of purchase up to the £1m AIA cap (shared across a group), with the balance entering the special-rate pool. Tax treatment is for your accountant; we point to the mechanism, not the outcome.

Which businesses this band suits

A megawatt-plus system suits organisations with either very large daytime loads or very large amounts of space, and ideally both. The economics turn on self-consumption: every kilowatt-hour you use on site displaces grid electricity at your full import rate, while exported surplus earns far less and, against an export limit, may not leave the site at all. So the strongest candidates are the ones that consume what they generate during the day.

  • Very large logistics and distribution. Big-shed estates and major distribution parks have the roof area to host a megawatt and, increasingly, the chiller, conveyor, charging and handling loads to absorb it. The roof is already there, which makes the rooftop route the default to test first.
  • Cold and chilled storage, and food production. Refrigeration and process loads run hard through daylight hours, giving high self-consumption and a strong fit with a large array plus storage to ride network-charge peaks.
  • Heavy manufacturing and process sites. Steady, high daytime demand is close to the ideal load shape for solar. At this scale storage and demand management add a second layer of value through the charging position.
  • Ground-mount on owned land. Where roofs cannot host a megawatt but you hold the land, a ground array on roughly 2 to 2.5 hectares per MW is the route. It carries more civils and a more involved connection, and it depends on grid capacity at the point of connection, which is why we model the site before committing to it.
  • Multi-site portfolios. Estates, retail and industrial portfolios and public-sector campuses often reach a megawatt across several roofs rather than one. One coordinated programme, designed and procured together, beats a scatter of separate jobs.

If your site is large but your daytime demand is not, that is not a dead end; it changes the route. A storage-led design, an export-limited connection, or a PPA where a developer monetises the roof can still make the space work. The job at this scale is to match the system to the load and the grid, and we model your half-hourly data to find which of those routes fits before any commitment.

A commercial solar installation in the 1 MW and above range
FAQ

Commercial solar at 1 MW and above: common questions

As an indicative figure, roughly 1,665 to 1,850 panels for a 1 MW (1,000 kWp) system, based on commercial modules of 540 to 600 W, which work out at about 1.7 to 1.85 panels per kWp. Higher-wattage modules mean fewer panels for the same capacity. This is an engineering rule of thumb for bracketing a project; the exact count comes from the module we specify and a measured roof or site layout, not from a standard figure.

On a flat commercial roof, allow roughly 5,000 to 7,000 m² of usable area per MW once row spacing and access are included. As a ground-mount array the same megawatt needs roughly 2 to 2.5 hectares, because ground systems are spaced more widely to avoid row shading and to allow maintenance access. These are indicative planning figures; usable area depends on roof obstructions, orientation, structural capacity or, for a ground site, the land and its connection point. A measured survey replaces the rule of thumb.

It depends on the space you have and the grid at your connection point. A rooftop array reuses an existing structure and sits behind your meter for direct self-consumption, but depends on the roof's load capacity, age and layout. A ground array suits sites with land but insufficient roof, at the cost of more civils, fencing and trenching, and a connection that depends on local network capacity. The two routes have genuinely different cost and timeline shapes, so we model both against your site and your half-hourly demand before recommending one.

We do not publish a price per kilowatt-peak at this scale, because at a megawatt the cost is driven by the things around the panels: the grid connection (often the largest single variable, especially for a high-voltage connection or where reinforcement is needed), the rooftop-versus-ground-mount route, the inverters and AC system, access and structure, and any battery storage. Per-kilowatt cost does tend to fall as the system grows, but only directionally, and a connection cost can pull against that on any given site. The figure that goes in a board paper is survey-led, from a PV*SOL model of your specific site. For payback and return, see our finance and ROI and payback pages.

Plan for a programme measured in many months rather than weeks, and at this scale it is the grid connection that paces the calendar more than the build. The physical install of a megawatt array is a matter of weeks once on site, but it sits at the end of a longer sequence: a G99 connection application and the DNO's network studies, planning permission (a ground-mount field or a large array can need full permission rather than permitted development), any structural or land survey, procurement of modules, inverters and switchgear, and mandatory witness testing before the network operator will let you energise. The recent move to a readiness-based connections queue means projects that can show planning progress and land control are prioritised, so starting the grid and planning conversations early is what shortens the overall timeline. We give you an indicative programme against your specific connection and site at survey; it is sequenced around the connection because at this scale that is the longest lead time on the job.

Get a commercial quote

Your size and your figure come from the survey, not a band.

These bands are a way to navigate. The system we actually design comes from your half-hourly consumption and an on-site drone survey, modelled in PV*SOL, with the figure built for your site rather than read off a price list.

  • Sized to your consumption, not your roof area
  • On-site 3D drone survey and PV*SOL model
  • Over 50 kWp, outside MCS